Hey, guys, do you know how LT & HT poles are erected? Let me share 08 steps with you.
The first step is land size, 0.5-meter length, and 0.5-meter width land size are needed.
The second step is the depth of digging,1/6th part of the pole. (Therefore, for the 8-meter pole, a 1.33m part will go underground).
The third step is Pole and Baseplate, The base plate is made up of stone. 450mm in length and width. After digging the base plate is kept at the bottom.
The fourth step is pole installation, Pole is installed in two ways, one is through labor with some ropes and a ladder & the way is by crane.
The fifth step is Bricks and Mud. Put 60 % bricks and 40 % mud layer-wise, after putting compress it by using the rod.
The sixth step is Fixing the cross arm.
The seventh step is the Fixing Pin Insulator.
The eighth step is the Placing of the Conductor.