Tests are to be conducted on wiring installations, select one of following

All QuestionsCategory: Electrical Estimating And CostingTests are to be conducted on wiring installations, select one of following
Rajasri Mundrathi Staff asked 3 years ago

Options:
a) Testing of polarity of non-linked sps(single pole-switches)
b) Testing of earth continuity path
c) Testing of earth resistance
d) All of these

1 Answers
Rajasri Mundrathi Staff answered 3 years ago

The correct answer is
All of these