Hello everyone, in this article I will discuss the estimation costing of overhead service for a single phase and three phase with example. You can also catch me @ Instagram – Chetan Shidling.
Before starting the article if you want to watch a video related to electrical estimation and costing, you can watch my YouTube videos – Click Here.
Also read – Battery Management System Questions And Answers.
Estimation Costing of Overhead Service
First, I will discuss what is overhead service mains.
The name overhead says that the conductors are drawn from above the ground level. The overhead line consists of service cables, reel insulators, broken insulators, messenger wire, GI pipe, service pipe, etc.
The advantages of overhead service mains are easy to erect, easy to find fault, the cost is less, etc and the disadvantages of overhead service mains are it is not safe, affected by sun or rain, ugly appearance, etc.
Single Phase Overhead Service Mains Calculation
Q: Prepare a list of material and estimate the cost for providing service connection to a building at 240 V single phase 50 Hz having a light and fan load of 2 KW and heating load of 2 KW. The supply is to be given from an overhead line 20 m. away from the building.
Solution: Materials used for service connection :
To calculate the size of the wire first you need to calculate the total connected load in the house and then calculate the load current of the house using proper formula.
Connected load = lighting load + heating load
= 2 KW + 2 KW = 4000 W
See a total load of house is 4000 W, multiply it by a factor of safety, the factor of safety means we should consider future load, now itself I will consider future load double of the present, so I will multiply by 2.
Keeping in view the future additional demand ( say 100% ) lets the future load be twice the present load (i.e. a factor of safety of 2). i.e. 2 × 4000 W = 8000 W.
Load current in amperes = Load in watts/Rated voltage
= 8000/240
= 33 Amps.
The load current of the house is 33 Amps, now by see the wire table you can find the size of the wire. Watch my video how to find the size of the wire – Click Here
The size of the aluminum cable is 10 sq mm from the wire table.
(a) The length of cable required
= (20 + 6 + 3 + 4) × 2
= 66 m
We should calculate the length of cable from low tensions lines to the consumer meter board, below I will provide formulas on how to calculate the length of cable.
Note: Lenght of the cable = Horizontal length (20 m) + Looseness and meter board connection (6 m) + Service pipe lenght (3 m) + Pole side connection (4 m)
Horizontal length – Length of cable from a pothead up to service pipe.
Looseness and meter board connection – length of cable from the end of the service pipe to the meter board.
Service Pipe – The cables are drawn inside the service pipe, so we should consider that length also.
Pole side connection – The cables used to connect low tension lines to pothead that length also we should consider.
(b) No of Break Insulators = 2 Nos
The number of break insulators required is 2 No. Only two break insulators are used in overhead service mains. one insulator at the pole side and another insulator at the meter board side. Break insulators are used to isolate messenger wire from the pole and also to give support for messenger wires.
(c) No of Reel Insulators = 2(20 + 6) = 52 Nos
The number of reel insulators required is 52 No. The purpose of reel insulators is to provide some distance between two conductors and it will also avoid short circuits between two conductors if both the conductor’s insulation has been damaged.
(d) 10 SWG G.I wire for messenging = 22m = 2 kg.
The purpose of messenger wire is to give support to the reel insulators and also to the service cables.
(e) 30 mm PVC pipe of 2 m and bends of 3 Nos.
(f) 40 mm G.I pipe of 3 mm thick 1.8 m for supporting.
(g) 500 mm × 500 mm × 45 mm WVTWB – 1 No.
(h) 40 mm G.I pipe 2.5m and l kg 8 SWG G.I. wire for earthing.
(i) 30 A fuse of 2 Nos and Miscellaneous materials.
Miscellaneous materials mean nut, bolt, etc.
These are the Materials required.
Costing Of Single Phase Overhead Service Mains
SI.No | Particulars | Unit | Quantity | Rate In Rupees | Cost In Rupees |
01 | 10 sq mm aluminium 11000 v grade double sheathed PVC cable | 100 M (coil) | 66M | 1800 | 1188.00 |
02 | 1.1 KV porcelain break insulator | No’s | 2 | 10.00 | 20.00 |
03 | Reel insulators | No’s | 52 | 2.00 | 104.00 |
04 | 10 SWG GI wire for messenging | Kg | 2 | 100.00 | 200.00 |
05 | 40 mm 3 mm thick GI pipe for supporting | M | 1.8 | 375.00 | 675.00 |
06 | 30 mm PVC pipe 2 mm thick for servicing | 3 M | 2 M | 65.00 | 43.33 |
07 | PVC bends | No’s | 3 | 10.00 | 30.00 |
08 | 500 * 500 * 45 mm well seasoned varnished teak wood (WVTB) | No | 1 | 600.00 | 600.00 |
09 | 40 mm GI pipe 3 mm thick for earthing | M | 2.5 | 375.00 | 937.50 |
10 | 8 SWG GI wire for earthing | Kg | 1 | 150.00 | 150.00 |
11 | 30 A 500 voltage grade porcelain fuse | No’s | 2 | 100.00 | 200.00 |
12 | 12.5 mm dia 300 eye bolt nuts of M.S | No’s | 2 | 50.00 | 100.00 |
13 | Miscellaneous materials such as binding wire clamps for pole and service pipe bolts, nuts, coal, salt, etc. | Lump sum | 525.67 | ||
14 | Labour charges | ||||
(a) for serving and earth work | 700.00 | ||||
15 | Contingencies and unforesen things @ 5% on above amount. | 260.10 | |||
Total= | 5460.00 |
Three Phase Overhead Service Mains Calculation
Q: Three phases overhead service connection: select the size and prepare an estimate for overhead service connection to feed power supply to a factory of 10 HP load for a distance of 10 meters.
Solution: Materials used for service connection.
Assuming a supply voltage of 400 V, p.f = 0.8 and the efficiency of the load is 80%.
Current = (10×735.5)÷(0.8×0.8×400×√3) = 16.6 Amps
Keeping view the future additional demand says 100% let the future load be twice of present load or factor of safety as 2, the current rating is 33A.
The size of the aluminum cable required is 10 sq mm.
(a) Lenght of the cable = 10+3+3+4 = 20 × 4 = 80 m.
Note: Lenght of the cable = Horizontal length (10 m) + Looseness and meter board connection (3 m) + Service pipe lenght (3 m) + Pole side connection (4 m).
(b) G.I Messenging wire = 10 + 1 = 11m = 1kg.
(c) No of Break Insulators = 2 Nos.
(d) No of Reel Insulators = (10+3)4 = 13 × 4 = 52 Nos.
(e) 30 mm PVC pipe of 2 m and of 3 bends.
(f) 50 mm G.I pipe of 3 mm thick 1.8 m for supporting.
(g) 500 × 500 × 65 m WVTWB – 1 No.
(h) 40 mm G.I pipe 2.5 m and 1 kg 8 SWG GI wire for earthing.
(i) 30 A fuse unit – 3 Nos.
(j) M.S. clamps with nuts and bolts – 2 sets and miscellaneous materials.
Costing Of Three Phase Overhead Service Mains
SI.No | Particulars | Unit | Quantity | Rate in rupees | Amount in rupees |
01 | 10 sq mm aluminium cable of 1.1 KV voltage grade, double sheathed | 100M (coil) | 80 M | 1800.00 | 1440.00 |
02 | 1.1 KV porcelain break insulators | No’s | 2 | 10.00 | 20.00 |
03 | Porcelain reel insulators | No’s | 52 | 2.00 | 104.00 |
04 | 10 SWG GI messanging wire | Kg | 2 | 100.00 | 200.00 |
05 | 30 mm PVC pipe of 2 mm thick, for servicing | 3 M | 2 | 65.00 | 130.00 |
06 | PVC bends for 30 mm PVC pipe | No’s | 3 | 10.00 | 30.00 |
07 | 50 mm GI pipe 3 mm thick 1.8M for supporting | M | 1.8 | 495.00 | 891.00 |
08 | 500 * 500 * 45 mm WVTWB | No | 1 | 600.00 | 600.00 |
09 | 30 A porcelain fuse unit 500 Vg | No | 3 | 100.00 | 300.00 |
10 | 40 mm GI pipe 3 mm thick | M | 2.5 | 375.00 | 937.00 |
11 | 8 SWG GI wire for earthing | Kg | 1 | 150.00 | 150.00 |
12 | 12.5 mm dia 300 mm eye bolt nuts of M.S | No | 2 | 50.00 | 100.00 |
13 | Miscellaneous materials such as binding wire, nuts, bolts, cement, salt, coal, etc. | Lump sum | 298.00 | ||
14 | Labour charge | ||||
(a) For earthing | 300.00 | ||||
(b) For servicing | 700.00 | ||||
15 | Contingencies and unforseen things @ 5% on above amount | 260.00 | |||
Total= | Add all |
I hope this article may help you all a lot. Thank you for reading. If you have any doubts related to this article “estimation costing of overhead service”, then comment below.
Tag: Estimation costing of overhead service.
Also, read:
- 10 Tips To Maintain Battery For Long Life, Battery Maintainance
- 10 Tips To Save Electricity Bills, Save Money By Saving Electricity
- 100 (AI) Artificial Intelligence Applications In The Automotive Industry
- 100 + Electrical Engineering Projects For Students, Engineers
- 1000+ Control System Quiz, Top MCQ On Control System
- 1000+ Electrical Machines Quiz, Top MCQs On Electrical Machines
- 1000+ MATLAB Simulink Projects For MTech, Engineering Students
- 50 Tips To Save Electricity At Home, Shop, Industry, Office
- 50+ Question And Answer On The Substation, Electrical Question
- 500+ Matlab Simulink Projects Ideas For Engineers, MTech, Diploma
- 500+ Projects For Diploma Electrical, Electronics Student, Diploma Project
- Active Cell Balancing Using A Flyback Converter Simulation In Matlab Simulink
- AI Artificial Intelligence Applications In Electric Vehicles | Future?
- AI Tools For Electronic Circuit Design, Which Is Best?
- Applications Of Artificial Intelligence (AI) In Renewable Energy
- Artificial Intelligence-Based Electrical Machines & Drives
- Automotive Industry Or VLSI Chip Industry ? Which Is Best?
- Basic Electrical Engineering, Terms, Definitions, SI Unit, Formula
- Basic Electrical Quiz, Take Online Test On Basic Electrical, Electrical Quiz
- Battery C Rate Online Calculator With Time Calculation